Sample report

DLP inspection, example extract

This is what a defects liability period inspection report from SML looks like. Every home gets its own schedule, with photographs, a risk rating for each item and a clear order of work, so it can go straight to the contractor before the defects period closes.

Example extract, prepared for illustration. Fictional property and findings.

1. Scheme details

Report referenceSML EX DLP 014
SchemeExample Court, 12 new build homes (fictional)
ClientExample Housing Association
Defects period endsIn eight weeks from the inspection
Inspection typeVisual, non intrusive, every room and external areas
Homes inspected12 of 12, plus communal areas
Prepared bySurveyor

2. Summary

Twelve homes and the communal areas were inspected. Forty one items were recorded across the scheme. Three are rated red and need the contractor to attend before the defects period ends, because they could let water in or affect safety. The rest are workmanship and finish items that the contractor should clear in the same visit.

RatingWhat it meansItems
RedAttend now. Water ingress, safety or a failing component3
AmberFix within the defects period. Workmanship or wear that will get worse17
GreenCosmetic. Clear in the same visit21

3. Schedule extract, Plot 7

RefLocationItemRating
P7.01BathroomSilicone to bath edge split at corner, water getting behind tilesRed
P7.02KitchenExtractor duct not connected to outlet, discharging into the voidRed
P7.03Bedroom 2Window does not lock fully, keep needs adjustingAmber
P7.04HallSettlement crack above door lining, about 1 mmAmber
P7.05Rear gardenPaving slab rocking by back doorAmber
P7.06LandingPaint run on skirtingGreen

4. Recommended order of work

  1. Reconnect the kitchen extractor duct and check the other plots of the same house type.
  2. Remove and renew bath and shower sealant where split, and check the tile backing is dry.
  3. Adjust windows and doors, then make good cracks and decoration in one visit.
  4. Reinspect the red items before the defects period closes and sign them off.

Full reports include a photograph for every item, a schedule for every home and a scheme summary the client can hand straight to the contractor.